Reply To: Complete Through date in Gantt Chart after status date for tasks starting late

Home Forums Discussion Complete Through date in Gantt Chart after status date for tasks starting late Reply To: Complete Through date in Gantt Chart after status date for tasks starting late

#413737
Thomas Boyle
Guest

Sudhakar – Indeed, this is “normal” for most users of MSP, since as Sai points out, the Duration is the same. This is an opportunity for you to confirm whether that is the reality. For continuous work, a “Complete Through” date to the right of the Status Date indicates that the Remaining Duration of the Task is LESS THAN the interval from the Status Date to the task’s Finish. I.e. in light of the reported progress, the scheduled Finish date may be conservative, and the task’s overall Duration may be too long.