Reply To: Complete Through date in Gantt Chart after status date for tasks starting late

Home Forums Discussion Complete Through date in Gantt Chart after status date for tasks starting late Reply To: Complete Through date in Gantt Chart after status date for tasks starting late

#413743
Carlos Santos
Guest

Hi Daril

If I understood your comments we should not have progress after the status date.
We can not track the future!
In your hypothetical case 75% complete that thru the SD, I think we should mark task on track and then update the finish of the task (remained duration, earlier finish)
Working on Gantt Tracking View.

Kind regards,

Carlos