Angeline, try this. Enter the task with the proper task duration. Then make sure you enter the hours when you assign the resource. You can’t do this directly assigning the resource in the task sheet, but:
Use the Assign resources dialog box and enter 32h in the Units column
Use the split screen on a task or Gantt chart with the Task Form, and enter 32 in the work column with the resource
Use the Task Information box and enter 32h in the Units column

You will want to make sure that the Effort Driven flag is set to No, which you can’t do on a Fixed Work task type. I suggest Fixed Units but Fixed Duration also works.

Hope that helps…good luck