Loading...
Quick Links

Reply To: % Complete – MS Project 2013

Home Forums Discussion % Complete – MS Project 2013 Reply To: % Complete – MS Project 2013

#413758
Abdul Rahman
Guest

Hi Oliver,
Thanks for the response, the scenario is, I’m entering manually the % Complete values as reported by resources on their respective tasks. The plan is manually scheduled and I’m not tracking resources or their working hours. Its a very loose matrix organization. Hence my job is to track the % complete of all the projects reported to me, hence using percent complete to do this job, as I update the % Complete for any job the summary % complete is updated, which I’m taking into account. Your suggestion, please.