Thanks for the immediate reply. Sorry, maybe you misunderstood me.

First step, I’ve created a new Report for Earned Value because to make it more presentable, graphs and etc.
Second Step, I want to include field ‘Status Date’ but cannot find in the the Field List.

As per your instruction, I’ve tried to customize outline code and rename it to Status Date or any name but it does not exist in Field List when creating Earned Value Report. I sent this concern to John Riopel, since he presented EVM in MPUG but he refer me to the discussion group which happen you reply. If you have time, in his graph, it shows EV, AC and PV graph horizontal line plus Status Date in Vertical Line.