Hi Norman. So two things to summarize here. First, yes dynamic schedules are built all the time. Second, yes you can create a project schedule for selected department tasks. The problem comes in trying to create both a dynamic schedule and for only selected department tasks. Dynamic schedules require tasks with dependencies and accurate task updates. As tasks move, the remaining schedule reflects the moves. If you don’t have all the required tasks then you can’t create a dynamic schedule. Hope that helps…