Hi Cory!

I am working on a program with 8 projects and I use a single sheet. The way we do it is to have it deliverable oriented where we only track the deliverables for each project and there dependencies. The low level tasks to create the deliverables is up to the project managers to track. I would recommend to check out Eric Uyttewall´s book Forecasting Programs which provides some real good hands-on advice on how to set up programs.

Good luck!