Home › Forums › Discussion › MS Project 2016 › Reply To: MS Project 2016
Gerald, great question. There are tricks such as active/inactive to identify what-if tasks. Reality is that an active 5000 line project will be difficult whatever you do (in my opinion of course). I might suggest setting a date or better yet a milestone/phase gate to begin a new schedule. Modify the original up to the stage gate, then start a new schedule after that date. That way you are working one schedule for each timeframe. Hope that helps…