Reply To: Visualization with MS Project

Home Forums Discussion Visualization with MS Project Reply To: Visualization with MS Project

#413927
Larry Christofaro
Participant

Ido, the O365 version of Project (Project for Office 365) has a Task Board that gives you a lot of what you are asking. It is an agile type of solution with drag and drop tasks. That in combination with the Task Board Sheet for durations can provide a pretty good visual. Unfortunately this is the only version of Project that provides these features. Hope this helps…