Reply To: MS Project Professional 2010. Rescheduling projects in Gantt Chart view.

Home Forums Discussion MS Project Professional 2010. Rescheduling projects in Gantt Chart view. Reply To: MS Project Professional 2010. Rescheduling projects in Gantt Chart view.

#414104
Larry ChristofaroLarry Christofaro
Participant

I can see your issue. Project allows you to move tasks or move the entire project with the Move Project command. Unfortunately the Move Project doesn’t move sub-projects. But, you can move the sub-project by having that project open as one of your active projects. Once moved, it will be reflected immediately in the master project. Hope that helps…