Reply To: MS Project 2016

Home Forums Discussion MS Project 2016 Reply To: MS Project 2016

#414114
Nishtha Narryani
Guest

Answer to your questions:
Are you only opening the one project? No, wherever the resource is linked, all the files are open
Are you using a resource pool? Yes
Are you using Project Online or Project Server? – It’s not online for sure, I have it on installed it in two individual systems and both are connected through server.

Project only manages resource allocation for open projects unless you are using a resource pool or Online/Server. Please provide additional information if you are still having this issue.