Reply To: Critical Path MSP Professional 2013

Home Forums Discussion Critical Path MSP Professional 2013 Reply To: Critical Path MSP Professional 2013

#414118
Sai PrasadSai Prasad
Participant
  • Community Leader
  • Forum Pro

Critical path uses different factors of task namely start, finish, dependency types, leads/lags and constraints. Critical path is calculated based on the early start and finish, late start and finish of each task and you can force a task to be in/out of the critical path.