Reply To: Creating project inputs in hours rather than days

Home Forums Discussion Creating project inputs in hours rather than days Reply To: Creating project inputs in hours rather than days

#414163
Jigs GatonJigs Gaton
Member
  • Author
  • Forum Pro

Liz, yes you can enter hours in many ways, and in many different places. Easiest? Just type Xh in the Duration column where X=hours, or do the same wherever you see the Work column. For example, using Task Details you can have a duration of 1 day, but assign resources to the task in hours (ie. me = 4h, you = 4h). Hope that helps!