Home › Forums › Discussion › resource with 24/7 calendar with varying availability during the day › Reply To: resource with 24/7 calendar with varying availability during the day
Shamim, I know this is not exactly what you are asking but I tend to try a “keep it simple” approach first if it works. What about just assigning the four loggers as a single team and then either know that one of them is a night shift worker or manually reassign based on shift once the logging task is near-term? There might be an option using resource leveling, maybe along with a single night shift resource, but that depends on specific results. Hope that helps…