Reply To: Microsoft Project 16 -populating custom field with Month of Task Start Date

Home Forums Customization Microsoft Project 16 -populating custom field with Month of Task Start Date Reply To: Microsoft Project 16 -populating custom field with Month of Task Start Date

#414395
Ismet Kocaman
Guest

The following formula entered to a custom text field (e.g. Text1) will return three-letter month names to the field:
Left( ProjDateConv( [Start], pjDate_mmm_dd), 3 )

Hope this helps.
Ismet