Reply To: Added Resource Vacation Time to a Project

Home Forums Discussion Added Resource Vacation Time to a Project Reply To: Added Resource Vacation Time to a Project

#414424
Larry Christofaro
Participant

Unfortunately not without the ability to edit enterprise resources. I’ve suggested using a special vacation project with a higher priority for customers using resource leveling. You can still use that for other customers but it won’t reduce demand for those periods. Not great news but that’s the way it works. Resources belong to the enterprise and not a particular project. Hope that helps…