Carlos;
Its been a while since I looked at this, but I believe PWA has a configuration option to define the fiscal year periods. If you are using PWA, click the gear icon to access settings and you’ll find something like “Manage Fiscal Periods”. (Not sure of the exact wording)
Once in there you can define standard period structures like 5-5-4, but I also believe you can create custom periods based on manually entered dates.
While our organization didn’t use these periods for reporting, I believe that these defined fiscal periods can be used in reporting.
Hope this helps