Loading...
Quick Links

Reply To: Task type – Fixed Work – Changing duration with several resources assigned

Home Forums Discussion Task type – Fixed Work – Changing duration with several resources assigned Reply To: Task type – Fixed Work – Changing duration with several resources assigned

#414493
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Hi Kennet,

This is not a bug. This generally happens because the other resources of that task have non-working day on day one (check the resource calendar or the base calendar tied to these resources) and so the work has to be scheduled from the day two onward.

If this does not help, please send a upload the screenshot or let us know what was the work assigned to each resource when the task had 1 day as its duration.

Regards,
Sai