Loading...
Quick Links

Reply To: Task type – Fixed Work – Changing duration with several resources assigned

Home Forums Discussion Task type – Fixed Work – Changing duration with several resources assigned Reply To: Task type – Fixed Work – Changing duration with several resources assigned

#414496
Sai PrasadSai Prasad
Participant
  • Community Leader
  • Forum Pro

My answer is same “This generally happens because the other resources of that task have non-working day on day one (check the resource calendar or the base calendar tied to these resources) and so the work has to be scheduled from the day two onward.”

I have Greenshot installed (http://getgreenshot.org/), do a print screen and use Upload to Imgur to get the link to the uploaded image (like this https://i.imgur.com/X76v0FC.png)