Reply To: Task type – Fixed Work – Changing duration with several resources assigned

Home Forums Discussion Task type – Fixed Work – Changing duration with several resources assigned Reply To: Task type – Fixed Work – Changing duration with several resources assigned

#414496
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

My answer is same “This generally happens because the other resources of that task have non-working day on day one (check the resource calendar or the base calendar tied to these resources) and so the work has to be scheduled from the day two onward.”