Reply To: Task type – Fixed Work – Changing duration with several resources assigned

Home Forums Discussion Task type – Fixed Work – Changing duration with several resources assigned Reply To: Task type – Fixed Work – Changing duration with several resources assigned

#414497

Hi Sai,

Its not because the other resources have non-working days.
Let me explain.

Task: FD – Duration 1 day – 2 resources
Ress M-T-W-T-F
KB 3-0-0-0-0
Gru 5-0-0-0-0

Same task, but duration is changed from 1 to 5 days.
Ress M-T-W-T-F
KB 3-0-0-0-0 (Work is NOT distributed – WHY?)
Gru 1-1-1-1-1 (Work is equally distributed)

It seems like only the highest workload (5 hours in this case) is equally distributed.

Hope this make sense to you.

Br Kennet