Reply To: Task type – Fixed Work – Changing duration with several resources assigned

Home Forums Discussion Task type – Fixed Work – Changing duration with several resources assigned Reply To: Task type – Fixed Work – Changing duration with several resources assigned

#414499
Sai PrasadSai Prasad
Participant
  • Community Leader
  • Forum Pro

Daryl is right. Changing the duration affects the work assigned only to the assigned resource driving the task finish date. The workaround is to change assignment finish date of the other resource to task finish date so that Project can spread the work evenly till the finish date.