Home › Forums › Discussion › Task type – Fixed Work – Changing duration with several resources assigned › Reply To: Task type – Fixed Work – Changing duration with several resources assigned
Hi
I did different way
Set TASK Fixed Units 1 day duration
Then Advance tab set to fixed duration
Assign resources A 3h. and B 5h. Ok. Task maintain 1 day duration
Now change duration to 5 days, warning reduce work check and all resources were distributed: A 0,6h
and B 1h.
Regards,
Carlos