Loading...
Quick Links

Reply To: Task type – Fixed Work – Changing duration with several resources assigned

Home Forums Discussion Task type – Fixed Work – Changing duration with several resources assigned Reply To: Task type – Fixed Work – Changing duration with several resources assigned

#414508
Carlos Santos
Guest

Hi Sai and Kennet

I m using PWA, MS Project 2016, version 1803
Sai
If you follow the steps:
Set Task Fixed Units 1 day duration, no resources assigned.
Then Advance tab set to fixed duration
Detail View: Assign resources A 3h. and B 5h. Ok. Task maintain 1 day duration
Now change duration to 5 days, warning: reduce work (check) and all resources were distributed: A 0,6h
and B 1h.

Have another solution:
File options set: Fixed Work
Add resources: A Max units 0,37 (3/8) and B Max units 0,63 (5/8)
Set task 1 day duration and assign resources A and B
Change duration to 5 days, warning check reduce work…
All resources were distributed

My email: cfsantos@netcabo.pt
Carlos
(from Portugal)

By the way
Sai waiting for Linkedin connection?

Kennet Do you have Linkedin account? Are you from Denmark?