Home › Forums › Discussion › Task type – Fixed Work – Changing duration with several resources assigned › Reply To: Task type – Fixed Work – Changing duration with several resources assigned
Hi Carlos, I use Project 2016 Professional whereas you are using Project Online Click-to-run desktop version, and this could be reason why we see different behavior. I will write to Microsoft to see what they have to say on this, and will help us to confirm if this is broken in Project 2016 Professional.