Reply To: MS Project Scheduling

Home Forums Discussion MS Project Scheduling Reply To: MS Project Scheduling

#414532

There are no orphans – all predecessors and successors are identified. With the exception of a few tasks which really are fixed duration. My summary tasks appear as fixed duration although there subtasks are fixed work. I did not set the type on the summary tasks and I don’t seem to be able to change it.