Loading...
Quick Links

Reply To: milestone finish at the end of a day

Home Forums Discussion milestone finish at the end of a day Reply To: milestone finish at the end of a day

#414561
Bob Hillier
Participant

Thanks Daryl. Some fiddling and I have it working. This may be too complicated (remembering KISS) but I know how to do it.

Why? My schedule has several milestones indicating various work groups complete. I want the a subsequent work group to begin at the beginning of the next day following a milestone completion.

Thomas – Create and assign an end-of-day-milestone calendar with custom time 4:59 PM to 5:00PM and 5:01PM to 5:02 PM (It seems I must define 2 shifts). Make the milestone dependency a FS+1m. It seems I must have the FS+1m to make the milestone schedule within the end-of-day-milestone calendar time.

Bob