Larry Christofaro
Participant

Hi Johnathan. That’s a tough question as Project isn’t exactly designed for or the best at doing invoice reporting, especially with the variations you have above. Dynamics is the project tool designed more for invoicing, but I realize that doesn’t help you here. Best I can tell you is to use cost resources for the fixed % charges and rates for others. Cost rate tables can help if one resource is involved in both, but that can get complicated pretty quickly. Good luck…