Jigs Gaton
Member
  • Author
  • Forum Pro

Chris, just do what you can to learn about Master Projects and Sub Projects (it’s in the interface). Basically, you create a master plan, imbed the subsets, and then use the master plan or any of the subprojects to change the data, and then data is automatically updated in both places (master and sub). It’s really easy but the only caveat is that you don’t want to move file locations after you set things up. Links are created, and while they can be broken / changed, it’s not intuitive. Also, hosting linked .MPP files on cloud services (with bad / iffy connectivity) can also be problematic. Just a few thoughts – best, Jigs