Home Forums Discussion Strange behaviour of task type Reply To: Strange behaviour of task type

#414890
Sai PrasadSai Prasad
Participant
  • Community Leader
  • Forum Pro

It needs to be on as when the remaining work of 24 hours (this is the Resource status) is moved to future date, the remaining duration (this is task status) will also be updated to 3 days. If this is off, updating remaining duration will be 2 days and remaining work will be 24 hours.