Daryl is correct on how the calendar works. One more thought on the days off. Since 10 + 4 is a two week period, you could setup a recurring non-working entry of four days that go every other week. Create the first time off event, then select the Details button and go every two weeks, four active days, to the duration of the project. Hope that helps.