Emma, I’ve done what u propose with files going back to 2010, and any major issues were cosmetic – where older files that are customized by the owners (currencies, columns, colors on the gantt, fonts, etc.) would display in unexpected ways when opened within the master (i.e. expanded out). If your files are standard project files (no customized formulas to fields or inserted VBA), u should be fine, but I think the only way to know for sure is to fire up 2016, insert the files one at a time, and check for functionality & integrity. But theoretically, what you want to do is possible. Best, Jigs