Hi

Thankyou. Jigs when you say no customised formulae, I was planning to use formulae within customised fields to create exception flags. What is the issue with these?

Would either of you have suggestions for doing this another way? The only thing I could think of was not ceating a master schedule and instead using export maps to put the sub project data into excel and then reimport or copy it into a single 2016 file?