Hi George, u could just create a master project and imbed them all as subs, and then just look at an expanded Gantt (View / Data / Outline / All Subtasks) and then use the Tables / Schedule and Sort to see them all listed by Start Date or whatever. I think that’s one way 🙂 Cheers, Jigs