Hi George;
To add to Jigs comments. You can also create a filter which could be applied to a task or resource usage view. This will limit the view to only the tasks you want to see.
I’d suggest starting with a filter with Actual Finish equals NA and Start is less than or equal to “Enter Todays Date”? .
Note that the Enter Todays Date in quotes followed by a question mark is entered into the values field. This will cause Project to prompt you for a date entry.

If not using a Resource Usage view, I’d also suggest grouping by Resource, which may necessitate adding the Project Name to the view columns so that you/the resource knows which project the task is associated with.

Hope this helps