Oswell;
The simple answer is yes, you use a Resource Usage view to see hours per day on each task for each resource. But you’ll need to tweak the view a bit. As a starting point;
* Set a filter to show only tasks that are not completed. This will allow project to display any task that is in progress or not yet started.
* Sequence the tasks by Start date. If it’s not in your view you can add this column to the left side of the view. Once the column is added, click the column header and select the appropriate order (ascending or descending)
* Adjust the Timescale in right side view to show days. I’d suggest configuring the middle to show weeks and the lower level to show days.

With the basic view established, you can use this as a starting point and tweak the view as needed by adding columns and adjusting column widths. If you plan to print the view project basically works on a “what you see on the screen is what prints” model. Meaning, if you’re seeing too many weeks in the right side view, adjust the left/right side column widths until you get what you want to see on one page. There are also Page Setup options (much like Excel) that can be adjusted as well.

I think this will get you to a good starting point. From there, tweak the view as needed until you get what you need.
And don’t forget to save the view!

Hope that helps