Reply To: The bar wont follow to early date

Home Forums Discussion The bar wont follow to early date Reply To: The bar wont follow to early date

#415091
Sai Prasad
Participant
  • Community Leader
  • Forum Pro

Take a look at this image – https://i.imgur.com/uU5qT3u.png

I have come across scenarios where the user presses the insert key by mistake when scrolling across the dates on the right side of the Task usage view. When insert key is pressed, Project considers that the work needs to moved to the next working day and sets 0 hours. In this image, on Monday 18th March, and Tuesday 19th March i pressed insert key and so the work got moved to the next working day. To fix this issue, you can either reset the duration to 0 days and change it back, or select those days on the right side of the Task usage viewand press Delete button.