Yes, Project Online connector (https://docs.microsoft.com/en-us/connectors/projectonline/) doesn’t support updating fields yet. You can use update enterprise fields as well as custom fields with workflow but one project at a time – https://docs.microsoft.com/en-us/office/client-developer/project/bulk-update-custom-fields-and-create-project-sites-from-workflow-in-project. So, you will still retain the Flow that checks out all projects, publishes and checks-in back. You write a workflow that gets triggered when check-in / publish event happens, and updates the enterprise fields or custom fields.