Reply To: How is Negative Slack managed ?

Home Forums Discussion How is Negative Slack managed ? Reply To: How is Negative Slack managed ?

#415258
Deborah Ray-Sims
Guest

Thanks for the response. The schedule is compressed and all task are set with constraint “as soon as possible” except for a few set at “must start on” Many tasks are being delayed which has pushed go-live date out adding to missed deadlines. Why is MS Project showing for example in the following task scenario the late start column is showing a 2017 date but the actual start date of the project is in 2018

Start Finish Late Start Late Finish Free Slack Total Slack
Mon 3/18/19 Fri 4/19/19 Thu 12/14/17 Fri 3/29/19 0 days -15 days