Reply To: Viewing subtask dependencies in Summary Task rollup

Home Forums Discussion Viewing subtask dependencies in Summary Task rollup Reply To: Viewing subtask dependencies in Summary Task rollup

#415302
Jigs Gaton
Member
  • Author
  • Forum Pro

Hi Ellen, if I understand what you want, I have to say that’s not a standard way to display tasks on a timeline. The assumption is that one summary bar follows another. You have summary bars, right? If so, you can change the display of the bar to better reenforce the connection. Right click on the right side of the Gantt, and select Bar Styles.Then adjust the Summary Appearance. Here you can also play with From and To to further customize the display. Best, Jigs