Reply To: Problem with MSProject Baseline Dates changing

Home Forums Discussion Problem with MSProject Baseline Dates changing Reply To: Problem with MSProject Baseline Dates changing

#415355
Heather Agee
Guest

If you are using existing tasks to create new tasks, just go to the Set Baseline utility, and hit “Clear Baseline”, then select “for selected tasks” so that you do not clear all task baselines. You have to be very careful with this, but that is a way to copy/paste activities and remove the baseline that was on the copied task. Then when you have updated the activity, you can “Set Baseline” “for selected tasks” and it will set the baseline for only the task(s) you have selected. I also recommend recording all baseline adds/changes/removes in a baseline change log.