Reply To: Industry projects

Home Forums Discussion Industry projects Reply To: Industry projects

#415416
Larry Christofaro
Participant

Jebir, I’m not sure what else to tell you. The task type would be the same, work is the amount of work required to complete, the duration would probably be the length of time to complete unless you are trying to keep the schedule short and want to get it done ASAP. In summary, set the task up based on the requirements of the task. I hope that helps…