Reply To: Project file corrupted – all tasks mixed up

Home Forums Discussion Project file corrupted – all tasks mixed up Reply To: Project file corrupted – all tasks mixed up

#415426
Larry Christofaro
Participant

James, are the IDs out of order or are the tasks rearranged to different IDs? If the former then it might be as simple as sorting by ID. You might also try a different View and Table if the table is corrupt. Now sure what version you are using but make sure you have all updates applied. Hard to tell if you already copied to a new schedule once. Rare bad luck to have a schedule get corrupted twice.