Loading...
Quick Links

Reply To: Industry projects

Home Forums Discussion Industry projects Reply To: Industry projects

#415434

Daryl;

Thank you for your response, seems that you got the situation!
But the real issue here is that the capacity is varying everyday and it’s for sure more than 60% or 70% allocated to operational work. Even resources don’t know their capacities because they are working on production process and unexpected actions are occurring every day and it’s their priority to deal with even if there are project task. So always, 99% of cases, operational work is prioritize even if it’s not scheduled and even if there is a project task scheduled.