Reply To: Looking for a way to override the Max Resource Units (utilization) at Task Level

Home Forums Discussion Looking for a way to override the Max Resource Units (utilization) at Task Level Reply To: Looking for a way to override the Max Resource Units (utilization) at Task Level

#415512
Larry ChristofaroLarry Christofaro
Participant

Hi John. Assigning resources with an override can be pretty simple depending on how you normally assign resources. If using the split screen, enter the Units at the time you assign the resource. If using the Assign Resources dialog box, enter in the Units field. Unfortunately you can’t override the max units when using the task sheet. You can also use these functions to override at a whole task level if already assigned, but will need to be careful of the task type not to change the task duration. Hope that helps…