Reply To: How to create a Custom View to Inspect a Task / Activity Predecessor & Successor

Home Forums Discussion How to create a Custom View to Inspect a Task / Activity Predecessor & Successor Reply To: How to create a Custom View to Inspect a Task / Activity Predecessor & Successor

#415529
Larry Christofaro
Participant

Hi Abhishek, great question. I don’t know of any way to do specifically what you are asking out of the box. There may be a way to help using VBA but I don’t know how (might be worth a search). Best answer I can provide is to try this.
1. Setup the view to display predecessors through Task Path (Format tab, Task Path, Predecessors). This is to help visualize the predecessors for a particular task.
2. Display the split screen with the Task Sheet on the bottom

Select a task with predecessors. Now using the Ctrl key, continue selecting each of the predecessor tasks identified in the task path.
Those tasks will display in the task sheet below with all the information available. Sorry, best I can think of without VBA. Hope that helps…