Loading...
Quick Links

Reply To: How to create a Custom View to Inspect a Task / Activity Predecessor & Successor

Home Forums Discussion How to create a Custom View to Inspect a Task / Activity Predecessor & Successor Reply To: How to create a Custom View to Inspect a Task / Activity Predecessor & Successor

#415544
Larry ChristofaroLarry Christofaro
Participant

1. From the gantt chart, select to show predecessors using the task path (Format tab, Task Path, Predecessors). If you don’t see this then you don’t have a recent enough Project version. This gives you a visual of all the predecessor of a particular task.
2. Split the screen to show the two panes (View tab, Details)
3. Select the bottom pane and display the Task Sheet table (Task tab, View Task Sheet)
4. On your upper Gantt chart view, use the Ctrl key to select a task with predecessors and all predecessor tasks (at the same time). The original task with predecessors will continue to highlight predecessor tasks while you continue to select those tasks.

The Task Sheet will show you all the predecessor tasks along with any column that you choose to include in the table.
Hope that helps…