Reply To: Task duration does not update based on 50% resource utilisation

Home Forums Discussion Task duration does not update based on 50% resource utilisation Reply To: Task duration does not update based on 50% resource utilisation

#415681
Larry Christofaro
Participant

Daryl has done a good job of explaining all the options and settings involved in assigning resources…which can get very complicated to the novice user so good going Daryl. One more thought that might help is to make sure you assign a units value at the time you assign the resource instead of after the fact. If you assign the resource as 50%, then it will assign the correct work without changing the duration with any of the task types. Two common ways to assign resources with the desired units in one step is to use the Assign Resources function or using a split screen with the task form on the bottom. Of course there’s also the assignment of additional resources which is dependent on the Effort Driven flag so be careful of that as well. Hope that helps…