Reply To: Inserting Task/Milestone as predecessor into middle of a task

Home Forums Discussion Inserting Task/Milestone as predecessor into middle of a task Reply To: Inserting Task/Milestone as predecessor into middle of a task

#415829
Larry Christofaro
Participant

Newbie but not a newbie question. Project provides a couple of solutions. You can adjust when the successor task starts by using either a number of days or a percent.
Task 1 with a negative lag of 3 days: 1FS-2 days
Task 1 at 50% of task 1 duration: 1FS-50%
Hope that helps…:-)