Reply To: Adding last status update to report.

Home Forums Discussion Adding last status update to report. Reply To: Adding last status update to report.

#415849
Larry Christofaro
Participant

David, best I can tell you in a quick look is to use a custom date field and have it equal to the Project Status date [Status Date]. Not sure you can retrieve it otherwise within Project. You can get it within Project Online or Project Server from the database.

Maybe someone has a shortcut. Hope that helps.