Tom Boyle
Guest

For “Visual Reports” (the pivot table/chart exports to Excel), then I think Larry’s already answered. You’ve got to get the status date into the task records through a custom field.

Inside MSProject, the Project Status Date is included among the “General:” fields that can added to Headers and Footers in the page setup dialog. That dialog is available for Reports as well as Views/layouts.